Construction

Until recently only 21 of the District’s 23 dams were classified as high hazard.  In February 2016 TCEQ re-classified the two remaining low hazard dams to a high hazard classification.  As of April 2016, 19 of the 23 dams have been upgraded in accordance with TCEQ regulations.  Construction will begin on the Dam #7 Modernization Project in June 2016.  Design is underway for Dam #8 Modernization, with construction expected to begin in late 2017.  Dams #10A and #10B (recently reclassified) will be evaluated for modernization in the near future. 

 

The U.S. Geological Survey (USGS) has installed rainfall and reservoir level gages at 22 District dams, as well as four new stream gages on Brushy Creek and one on Lake Creek.  Real time precipitation, reservoir elevation, and stream stage information is available on the District’s Flood Monitoring System, and can be accessed by clicking HERE.”  The current and archived information is also available on the USGS website, and can be accessed by clicking HERE.

 

Dam Status Construction
Contract
Construction
Start
Construction
Completion
Contractor
Dam 9 Complete $305,000 Aug. 2003 Dec. 2003 Ranger Excavating
Dam 12 Complete $553,698 Dec. 2004 Aug. 2005 DayCo Const. Co.
EWS - Phase I Complete $329,341 Dec. 2004 Sept. 2005 C. Fowler and Assoc.
Dam 11 Complete $854,698 Jan. 2005 Sept. 2005 DayCo Const. Co.
Dam 14 Complete $248,125 Feb. 2005 Sept. 2005 C.C. Carlton Industries
Dam No. 13A Complete $2,197,937 Sep. 2005 Dec. 2006 Chasco Constructors
EWS - Phase II Complete $655,003 Nov. 2005 May. 2007 C. Fowler and Assoc.
Dam 1 - Phase I Complete $1,203,238 Nov. 2005 Apr. 2006 Keystone Construction
Dam 6 - Phase I Complete $322,619 Nov. 2005 Aug. 2006 Keystone Construction
Dam 15 Complete $533,040 Nov. 2006 Jun. 2007 Austin Engineering Co.
Dam 20 Complete $348,100 Nov. 2006 Jun. 2007 MAC, Inc.
EWS - Phase III Complete $873,208 Dec. 2006 Sep. 2007 Keystone Construction
EWS - Phase IV Complete $266,200 Dec. 2006 Complete Keystone Construction
Dam 1 - Phase II Complete $382,285 Aug. 2007 Dec. 2007 Austin Filter Systems
Dam 6 - Phase II Complete $414,590 Sep. 2007 May. 2008 Mann Contractors, Ltd.
Dam 17 Complete $723,750 Dec. 2007 Sept. 2008 Austin Filter Systems
Dam 5 Complete $297,300 Aug. 2008 Dec. 2008 Austin Engineering Co.
Dam 2 Complete $443,200 Dec. 2008 Sept. 2010 Capital Concrete Contractors
Dam 16 Complete $797,400 Dec. 2008 Sept. 2009 Capital Concrete Contractors
Dam 19 Complete $637,690 Dec. 2007 Sept. 2008 Austin Filter Systems
Dam 14 Complete $279,025 Sept. 2009 April 2010 Patin Construction, LLC
Dam 4 Complete $289,385 Nov. 2009 May 2010 Ross Construction, Inc.
Dam 3 Complete $619,835 June 2010 Dec. 2010 Patin Construction, LLC
Dam 21 Complete $171,353 Sept. 2010 Feb. 2011 Capital Concrete Contractors
Dam 22 Complete $259,632 Sept. 2010 Feb. 2011 Capital Concrete Contractors
Dam 18 Complete $376,740 Dec. 2010 June 2011 Patin Construction, LLC
Dam 7 Under Construction
$17,819,000
June 2016
Late-Autumn 2017
ASI Constructors, Inc.
Dam 8 In Design TBD TBD TBD TBD

 Dam 22            In Design


Dam 101           In Design


Dam 102
         In Design